Will reconstruct the existing at grade expressway into a grade separated parkway expressway with interchanges. Construction funding is slated for fiscal year 2019 and 2020 which means construction could begin as soon as 2020 but with a project of this magnitude it could be up to 10 phases of construction and several years to complete. | Will reconstruct the existing at grade expressway into a grade separated parkway expressway with interchanges. Construction funding is slated for fiscal year 2019 and 2020 which means construction could begin as soon as 2020 but with a project of this magnitude it could be up to 10 phases of construction and several years to complete. The plan is to upgrade SR-37 from a surface expressway to a 4-lane parkway with controlled access interchanges landscaping and parkway features. Below is a list of the proposed improvements: | ||
*126th Street - teardrop roundabout interchange and diagonal on/off ramps | *Phase 1 (2017-2025) - Completed 2025 | ||
*131st Street - teardrop roundabout interchange and diagonal on/off ramps/collector Road | **126th Street - teardrop roundabout interchange and diagonal on/off ramps | ||
*135th Street - | **131st Street - teardrop roundabout interchange and diagonal on/off ramps/collector Road | ||
*141st Street - teardrop roundabout interchange and diagonal on/off ramps | **135th Street - right in/right out interchange with diagonal ramps (no bridge crossing or underpass) | ||
*146th Street (Campus Parkway) - teardrop roundabout interchange and diagonal on/off ramps | **141st Street - teardrop roundabout interchange and diagonal on/off ramps | ||
*Greenfield Avenue - teardrop roundabout interchange and diagonal on/off ramps | **146th Street (Campus Parkway) - teardrop roundabout interchange and diagonal on/off ramps | ||
*Town and Country Blvd - | |||
*Pleasant Street - teardrop roundabout interchange and diagonal on/off ramps | *Phase 2 (2027-2032) | ||
* | **Greenfield Avenue - teardrop roundabout interchange and diagonal on/off ramps - Proposed | ||
*Connor Street (SR-32) - teardrop roundabout interchange and diagonal on/off ramps | **Town and Country Blvd/Stoney Creek Rd - hybrid interchange with roundabouts and crossover connection route - Proposed | ||
**Pleasant Street - teardrop roundabout interchange and diagonal on/off ramps - Proposed | |||
**Connor Street (SR-32) - modified hybrid teardrop roundabout interchange and diagonal on/off ramps and slip ramps - Cherry Street ramps will provide connection to and from Connor Street connect - Proposed | |||
{| class="wikitable floatright" style="border-spacing: 2px; border: 1px solid darkgray;" | |||
|- border="0" style="text-align: center" | |||
| [[File:SR37Nob.png|700px|Roll Plot]] | |||
|- style="text-align: center" | |||
| SR-37 Noblesville Project Map | |||
|} | |||
===More Information=== | |||
*[https://www.hamiltoncounty.in.gov/999/SR-37-Project-Information Hamilton County Highway Department] | |||
*[https://www.in.gov/indot/about-indot/central-office/welcome-to-the-greenfield-district/state-road-37-improvement-project-in-noblesville/ INDOT SR-37 Improvements Page] | |||
*[https://www.in.gov/indot/files/SR-37-Plan-View-Roll-Plot_Jordan-Yaney.pdf Roll Plot PDF - Phase 2 Improvements (INDOT)] | |||
*[https://37thrives.com/ 37 Thrives] | |||
*[https://www.wthr.com/article/news/local/noblesville-state-road-37-construction-improvement-project/531-8cfec7a4-a346-4659-9f7e-2c7b07f87ef1 WTHR13 05/08/2026] | |||
[[Category:Indiana]][[Category:Projects]] | [[Category:Indiana]][[Category:Projects]] | ||
Latest revision as of 07:17, 2 June 2026
Will reconstruct the existing at grade expressway into a grade separated parkway expressway with interchanges. Construction funding is slated for fiscal year 2019 and 2020 which means construction could begin as soon as 2020 but with a project of this magnitude it could be up to 10 phases of construction and several years to complete. The plan is to upgrade SR-37 from a surface expressway to a 4-lane parkway with controlled access interchanges landscaping and parkway features. Below is a list of the proposed improvements:
- Phase 1 (2017-2025) - Completed 2025
- 126th Street - teardrop roundabout interchange and diagonal on/off ramps
- 131st Street - teardrop roundabout interchange and diagonal on/off ramps/collector Road
- 135th Street - right in/right out interchange with diagonal ramps (no bridge crossing or underpass)
- 141st Street - teardrop roundabout interchange and diagonal on/off ramps
- 146th Street (Campus Parkway) - teardrop roundabout interchange and diagonal on/off ramps
- Phase 2 (2027-2032)
- Greenfield Avenue - teardrop roundabout interchange and diagonal on/off ramps - Proposed
- Town and Country Blvd/Stoney Creek Rd - hybrid interchange with roundabouts and crossover connection route - Proposed
- Pleasant Street - teardrop roundabout interchange and diagonal on/off ramps - Proposed
- Connor Street (SR-32) - modified hybrid teardrop roundabout interchange and diagonal on/off ramps and slip ramps - Cherry Street ramps will provide connection to and from Connor Street connect - Proposed
| SR-37 Noblesville Project Map |