Northwest Indiana Projects: Difference between revisions
Jump to navigation
Jump to search
Created page with "This page will contain information regarding projects in the Northwest Indiana Metro Area This includes the cities of Hammond, Valparaiso, and Hobart IN. ==Current Projec..." |
|||
| Line 6: | Line 6: | ||
===Interstate 65 Widening=== | ===Interstate 65 Widening=== | ||
This will widen the freeway from just south of SR-2 to the US 30 junction from 4 to 6 lanes by adding one additional lane to the inside median between SR-2 to US231 and one additional lane along the shoulder between US 231 north to US 30. The project is currently under construction and is expected to be completed in 2018. [[File:nwin65.jpg|thumb|300px]] | This will widen the freeway from just south of SR-2 to the US 30 junction from 4 to 6 lanes by adding one additional lane to the inside median between SR-2 to US231 and one additional lane along the shoulder between US 231 north to US 30. The project is currently under construction and is expected to be completed in 2018. [[File:nwin65.jpg|thumb|300px]] | ||
===US 41 Widening=== | |||
US 41 Added Travel Lanes, | |||
Construct Turn Lanes | |||
From 1.48 mi S of US 30 (82nd | |||
Lane) to 0.83 mi S of US 30 | |||
(77th Ave) | |||
LaPorte .658 NHPP Safety | |||
Construction | |||
33957 / Init. CN $2,160,000.00 $540,000.00 $2,700,000.00 | |||
Revision as of 19:43, 24 March 2018
This page will contain information regarding projects in the Northwest Indiana Metro Area
This includes the cities of Hammond, Valparaiso, and Hobart IN.
Current Projects
Interstate 65 Widening
This will widen the freeway from just south of SR-2 to the US 30 junction from 4 to 6 lanes by adding one additional lane to the inside median between SR-2 to US231 and one additional lane along the shoulder between US 231 north to US 30. The project is currently under construction and is expected to be completed in 2018.

US 41 Widening
US 41 Added Travel Lanes, Construct Turn Lanes From 1.48 mi S of US 30 (82nd Lane) to 0.83 mi S of US 30 (77th Ave) LaPorte .658 NHPP Safety Construction 33957 / Init. CN $2,160,000.00 $540,000.00 $2,700,000.00